Is there a formal Web Project Process for new sites?
Project Process
Initiation Phase - Initial contact with Web Services
Request is placed online using our project request formDiscovery consultation is scheduled promptly based on client availability
Detailed needs analysis and requirements gathering performed
Basic scope and resource requirements are determined
Planning Phase - Feasibility Analysis, Prioritization and Project Plan
Priority assigned to project based on existing project load and associated University priorities
Formal Project Plan Draft is delivered to and agreed to by client
Project timeline, work allocation suggestions, and estimated costs
Agreement by client to conditions therein
Resource allocation and commitment from internal staff
Final Project Charter
Project Management System is configured
Design / Development Phase  Prototype to Alpha Build
Content obtained from client
Web Services develops the site prototype based upon stated requirements and needs analysis
Conduct the internal design review session
Conduct a prototype Demo Session or provide client with url to see the site in production
OPTIONAL - Revision cycle and change management process
Development / Revision Phase  Beta to RC Build
Full site developed from prototype to meet revision specifications
Integration of additional content from client and any approved revisions
Scripts, Database, and other technologies are fully unit tested
Site Review and sign off by the project team
Analytics must be integrated
Preflight / Implementation Phase - Client Acceptance and Training
Final site demonstration and review with client for preflight acceptance
Only minor adjustments and modifications are made as necessary
Client training is scheduled
Supporting Documentation is produced
Implementation / Closure Phase
Site Release Production Launch
Postmortem/ Closure session if needed
Lessons Learned Session
Client feedback gathered
Revision or maintenance cycle or schedule is established
All Project Management System tasks are verified, updated by assignees
PM verifies the project status, creates a full project closure report from the system and closes the project.
Last Update: 2009-04-23 3:39 PM